TL;DR

Initial commits for week 1 of Sprint 4.  Goals are to get our social media presence reestablished and get final orders of parts made.

Backlog – See Syndcon Task List tab for current sprint plan and Backlog tab for full backlog.

Reports

J.

Did

  • n/a

Will Do

  • Count all components and order additional materials if needed for 15 total units (sensor, tone ring)
  • Coordinate with Syndcon chair
  • Make template for stand up status update posts in WordPress
  • Confirm functionality for alternative exercise equipment (other bike)

Blocks?

  • none

Bryan

Did

  • n/a

Will Do

  • Count all components and order additional materials if needed for 15 total units (controller)
  • Install Glue between WordPress and social media (twitter/facebook)
  • Verify wordpress Template plugin
  • Confirm functionality for alternative exercise equipment (elliptical)

Blocks?

  • none