TL;DR
Initial commits for week 1 of Sprint 4. Goals are to get our social media presence reestablished and get final orders of parts made.
Backlog – See Syndcon Task List tab for current sprint plan and Backlog tab for full backlog.
Reports
J.
Did
- n/a
Will Do
- Count all components and order additional materials if needed for 15 total units (sensor, tone ring)
- Coordinate with Syndcon chair
- Make template for stand up status update posts in WordPress
- Confirm functionality for alternative exercise equipment (other bike)
Blocks?
- none
Bryan
Did
- n/a
Will Do
- Count all components and order additional materials if needed for 15 total units (controller)
- Install Glue between WordPress and social media (twitter/facebook)
- Verify wordpress Template plugin
- Confirm functionality for alternative exercise equipment (elliptical)
Blocks?
- none