TL;DR

Sad burn down chart is sad.  This was not a productive week for us.  We will be circling the wagons where engagement is concerned and narrowing our commitments to ensure next week is at least better in terms of finishing what we committed to.

Backlog – See Kanban 1.1 tab for current sprint plan and Backlog tab for full backlog.

Reports

J.

Did

  • Reached out over email to Alpha testers (8 opened, 1 has since posted play reports or to Discord #testing as requested)
  • Ordered and received Certificate of Good Standing from DC
  • Started work on remaining Alpha test license agreements

Will Do

  • Continue reaching out to Alpha testers
  • Create VA Articles of Organization
  • Continue work on remaining Alpha test license agreements

Blocks?

  • Need to get Alpha testers engaged

Bryan

Did

  • Posted challenge/question/activity for Alpha testers to FB (no responses, revising plan)

Will Do

  • Tag Alpha testers on first challenge/question/activity on FB

Blocks?

  • Need to get Alpha testers engaged
  • Greatly reduced availability (work trip)