TL;DR
This week marks the end of the first Kanban of the first iteration in PY19, so we are reloading the plan for Kanban 1.2. Our goal is to build on the success of Kanban 1.1 by sharing the results of testing to date (no new bugs reported, lots of #ExerfyingYourGames happening, happy users) and pressing for even more data from the Alpha Test.
Backlog – See Kanban 1.2 tab for current sprint plan and Backlog tab for full backlog.
Reports
J.
Did
- Got photos/comments from 3+ testers
- Got word that last outstanding license agreement is in the mail
- Gathered materials on using FB pages more effectively
Will Do
- Post first “How I Holoseat” post
- Distill FB Pages research into actionable tasks
- Start drafting Testimonial Page
Blocks?
- none, but working at greatly reduced capacity for the next couple of weeks
Bryan
Did
- none
Will Do
- Check the mail
- Send back last countersigned license agreements
- File for domestication in VA
- Follow up about trademark filings
Blocks?
- none